Garment Capacity & Cash Control Tower

Capacity

Capacity

Factory loading decisions for Base Plan - Week 32.

Base Plan

Scenario

Week 32

Planning

Mock

Data

Executive Summary

Capacity control view

Week 32 is the first low week. K-4 fabric is blocked, K-13 trims are pending, and the recovery path is to clear K-4 or pull K-8 forward.

First decision

Release K-4 fabric or prepare K-8 as the W32 fallback.

Utilization

63%

Idle Capacity

125k pcs

Lowest Utilization Week

W32

Pull-Forward Opportunities

K-8, K-12

Capacity Health

Weekly status row

W30

20-Jul to 26-Jul

92% utilized

8,000 pcs gap

W31

27-Jul to 02-Aug

85% utilized

15,000 pcs gap

W32

03-Aug to 09-Aug

63% utilized

36,630 pcs gap

W33

10-Aug to 16-Aug

76% utilized

23,760 pcs gap

W34

17-Aug to 23-Aug

88% utilized

11,880 pcs gap

Capacity Loading View

Daily combo capacity heatmap

Combo 7 and Combo 8 are the primary W32 exposure because K-4 cannot safely start until fabric readiness and cash cover are cleared.

Green >85%Amber 70-85%Red <70%
Combo03-AugW3204-AugW3205-AugW3206-AugW3207-AugW3208-AugW32Planner Signal
Combo 1
72%
74%
76%
75%
76%
78%
No first-order management action.
Combo 2
71%
72%
73%
73%
74%
75%
No first-order management action.
Combo 3
66%
67%
68%
68%
69%
70%
W32 underload watch after K-4 decision.
Combo 4
62%
63%
64%
65%
66%
67%
W32 underload watch after K-4 decision.
Combo 5
70%
71%
71%
72%
72%
73%
No first-order management action.
Combo 6
60%
61%
62%
63%
64%
65%
W32 underload watch after K-4 decision.
Combo 7
58%K-4
46%K-4
42%K-4
40%K-4
45%K-4
52%K-4
Primary W32 idle exposure caused by K-4 fabric readiness.
Combo 8
56%K-4
44%K-4
40%K-4
38%K-4
42%K-4
50%K-4
Primary W32 idle exposure caused by K-4 fabric readiness.
Combo 9
58%
59%
60%
61%
62%
63%
W32 underload watch after K-4 decision.
Combo 10
62%
63%
64%
65%
66%
67%
W32 underload watch after K-4 decision.
Combo 11
70%
71%
72%
72%
73%
74%
No first-order management action.
Combo 12
59%
60%
61%
62%
63%
64%
W32 underload watch after K-4 decision.
Combo 13
69%
70%
70%
71%
71%
72%
W32 underload watch after K-4 decision.
Combo 14
70%
70%
71%
71%
72%
72%
No first-order management action.
Combo 15
55%
56%
57%
58%
59%
60%
W32 underload watch after K-4 decision.

Capacity Exceptions

Gaps requiring management attention

No overloaded weeks in this base plan; the problem is underload.
WeekCapacity GapRoot CauseImpactSuggested Action
W32
125,000 pcs near-term exposureK-4 fabric 65%; K-13 trims 72%First low week; Combo 7 and 8 exposedSecure cash cover, release K-4 fabric, pull K-8 if needed
W33
23,760 pcsK-5 readiness pendingW33 stays at 76% unless trims closeChase K-5 trims and hold as capacity buffer
W35
29,700 pcsK-12 not yet pulled forwardSecondary idle exposure if W32 slips continueKeep K-12 ready as backup recovery load
W36
24,750 pcsFuture partial orders pendingFuture watch, not the first management decisionTrack readiness after W32 risks are cleared

Critical Capacity Risks

Exceptions first

W32 Readiness Gap

K-4, K-13

Action Required
Impact
125,000 pcs idle exposure starts here
Suggested Action
Release K-4 fabric and escalate K-13 trims

W32 Allocation Pressure

K-7, K-11

Action Required
Impact
Ready work exists, but combo and cash decisions are still needed
Suggested Action
Confirm Combo 13 and 14; clear K-11 vendor hold

W33 Buffer Risk

K-5

Watch
Impact
W33 capacity recovery depends on trim closure
Suggested Action
Chase trims and keep K-5 as the next load buffer

Pull-Forward Recovery

K-8, K-12

Healthy
Impact
Ready orders can absorb open combo time if K-4 slips
Suggested Action
Prepare K-8 first, keep K-12 as secondary fallback

Capacity Detail Table

Weekly load and driver detail

Week 32 opens by default so the K-4, Full Kit, cash, and pull-forward story is visible immediately.

WeekPlanned CapacityAvailable CapacityUtilizationGapPrimary Driver

W30

20-Jul to 26-Jul

91,000 pcs99,000 pcs
92%Healthy
8,000 pcs

K-1 and K-2 running

W31

27-Jul to 02-Aug

84,000 pcs99,000 pcs
85%Healthy
15,000 pcs

K-3 and K-6 loading

W32

03-Aug to 09-Aug

62,370 pcs99,000 pcs
63%Action Required
36,630 pcs

K-4 blocked, K-13 trims pending

Why It Matters

Related Orders

K-4 (At Risk - Full Kit), K-13 (At Risk - Trim Gap), K-7 (At Risk - Ship Date), K-11 (At Risk - Cash Hold)

Full Kit Impact

K-4 fabric is only 65% ready and K-13 trims are only 72%, so W32 starts without enough safe work.

Cash Impact

K-4 fabric release needs cash cover, and K-11 has a vendor hold risk.

Suggested Action

Arrange Rs 2.4 Cr working capital, expedite K-4 fabric, confirm K-7 allocation, and prepare K-8 as fallback.

Traceability

OrdersFull KitCapacityDashboardCashRecommendations

W33

10-Aug to 16-Aug

75,240 pcs99,000 pcs
76%Watch
23,760 pcs

K-5 readiness pending

W34

17-Aug to 23-Aug

87,120 pcs99,000 pcs
88%Healthy
11,880 pcs

K-8 and K-10 available

W35

24-Aug to 30-Aug

69,300 pcs99,000 pcs
70%Watch
29,700 pcs

K-12 not yet pulled forward

W36

31-Aug to 06-Sep

74,250 pcs99,000 pcs
75%Watch
24,750 pcs

Future partial orders pending