Cash constraint decisions for Base Plan - Week 32.

Base Plan

Scenario

Week 32

Planning

Mock

Data

Executive Summary

Cash control view

Cash becomes a production constraint when K-4 fabric release needs cover before receipts recover. The first negative date is 14-Aug and the prevention action is Rs 2.4 Cr cover before 10-Aug.

First decision

Secure Rs 2.40 Cr cash cover before 10-Aug.

Current Cash

Rs 3.80 Cr

Lowest Cash Position

-Rs 1.10 Cr

Negative Cash Date

14-Aug

Working Capital Required

Rs 2.40 Cr

Cash Flow Timeline

When cash becomes a production constraint

The timeline explains why the balance moves: fabric release, vendor hold, delayed receipts, and the bridge cover decision.

Positive cash zone

Opening cash is positive before material commitments land.

Negative cash zone

14-Aug is the first negative date and 21-Aug is the low point.

Recovery point

Receipts recover after the W32 production decision is due.

Major Events visible on timelineToday marker: 31-JulFirst negative cash date: 14-AugLowest cash point: 21-AugRecovery point: 28-Aug31-Jul: Opening cash position07-Aug: Fabric payment preparation14-Aug: Fabric payment for K-421-Aug: Lowest projected cash point28-Aug: Buyer receipts begin

Cash Health

Operating cash status

Current Position

Rs 3.80 Cr

Opening cash is positive

Near-Term Risk

Negative on 14-Aug

Supplier payments exceed receipts

Working Capital

Rs 2.40 Cr

Cover required before 10-Aug

Recovery Outlook

Positive by 28-Aug

Buyer receipts begin

Cash Constraint Drivers

Why cash becomes negative

DriverImpactOrders AffectedRecommended Action
Fabric Release
Part of Rs 2.40 Cr cover; K-4 fabric is blocked until cash is securedK-4, K-13Secure cash cover and release K-4 fabric
Vendor Hold
Ready work cannot convert into runnable work if payment or credit is not clearedK-11Negotiate vendor credit or approve release payment
Timing Gap
Material payments arrive before buyer receipts and push cash below zeroK-4, K-7, K-11Align receipts and arrange bridge funding

Cash Event Log

Sequence causing the constraint

DateEventAmountRelated OrdersEvent Type
31-Jul-2026Opening cash positionRs 3.80 CrK-1, K-2Opening Balance
07-Aug-2026Material advances for K-4, K-7, K-11Rs 1.20 CrK-4, K-7, K-11Fabric Payment
14-Aug-2026Supplier payments exceed receipts-Rs 0.40 CrK-4, K-13, K-11Cash Constraint
21-Aug-2026Lowest cash point-Rs 1.10 CrK-4, K-11Runway Low
28-Aug-2026Buyer receipts beginRs 0.60 CrK-1, K-3, K-11Buyer Receipt
04-Sep-2026Recovery after receiptsRs 2.10 CrK-5, K-7Factor Receipt

Daily Cash Flow Table

Operating detail behind the constraint

DateOpening CashInflowOutflowClosing CashMain Driver
31-JulRs 3.80 CrRs 0.00 CrRs 0.00 CrRs 3.80 CrOpening cash position
03-AugRs 3.80 CrRs 0.20 CrRs 1.40 CrRs 2.60 CrK-4 fabric release preparation
07-AugRs 2.20 CrRs 0.30 CrRs 1.30 CrRs 1.20 CrK-4, K-7, K-11 material advances
10-AugRs 1.20 CrRs 0.40 CrRs 1.20 CrRs 0.40 CrK-4 fabric release deadline
14-AugRs 0.40 CrRs 0.20 CrRs 1.00 Cr-Rs 0.40 CrSupplier payments exceed receipts
21-Aug-Rs 0.40 CrRs 0.40 CrRs 1.10 Cr-Rs 1.10 CrLowest cash point
28-Aug-Rs 1.10 CrRs 2.00 CrRs 0.30 CrRs 0.60 CrBuyer receipts begin
04-SepRs 0.60 CrRs 1.90 CrRs 0.40 CrRs 2.10 CrFactor receipts complete recovery

Critical Cash Risks

Exceptions requiring management action

K-4

Fabric release required

Action Required
Cash Impact
Fabric release increases the near-term cash requirement.
Working Capital Impact
Part of Rs 2.40 Cr cover
Suggested Action
Expedite fabric and secure cash cover by 10-Aug.

K-11

Vendor payment hold

Action Required
Cash Impact
Vendor hold requires payment or credit negotiation.
Working Capital Impact
Vendor credit or release payment
Suggested Action
Negotiate vendor credit or approve release payment.

K-13

Trim closure timing

Watch
Cash Impact
No special cash hold, but trim closure may need payment timing.
Working Capital Impact
Material closure timing
Suggested Action
Escalate trims and freeze start decision on 04-Aug.

Constraint Analysis

How cash stops production execution

K-4 cash to capacity chain

K-4 fabric releaseRs 0.8 Cr requiredCash turns negativeFabric not releasedK-4 cannot start125,000 pcs idle capacityLost throughput
Approve cash cover before 10-Aug

K-11 ready order hold

Vendor hold remains openReady order cannot runWeek 32 recovery work is delayedOpen capacity remains exposed
Negotiate vendor credit or approve payment

Timing gap to cash constraint

Material payments arrive firstBuyer receipts arrive laterCash turns negative on 14-AugFactory plan becomes cash constrained
Arrange Rs 2.40 Cr bridge cover

Receipt delay to throughput risk

Buyer receipts arrive after material paymentsCash cover is required before recoveryFabric release waitsOrders cannot start on planCapacity recovery is delayed
Bridge the timing gap and protect the W32 plan

Cash Detail Table

Expand the cash events that affect production

The first negative event opens by default so the K-4, Full Kit, capacity, and recommendation links are visible immediately.

DateEventAmountImpactRelated Orders
31-Jul-2026

Opening cash position

Healthy

Opening Balance

Rs 3.80 Cr

The base plan starts positive, but material advances are approaching.

K-1, K-2
07-Aug-2026

Material advances for K-4, K-7, K-11

Watch

Fabric Payment

Rs 1.20 Cr

Cash runway narrows before K-4 fabric release and K-11 vendor hold are cleared.

K-4, K-7, K-11
14-Aug-2026

Supplier payments exceed receipts

Action Required

Cash Constraint

-Rs 0.40 Cr

Cash becomes a constraint and can stop the production recovery plan.

K-4, K-13, K-11

Why It Matters

Orders Affected

K-4 (At Risk - Full Kit), K-13 (At Risk - Trim Gap), K-11 (At Risk - Cash Hold)

Full Kit Impact

K-4 fabric and K-13 trims remain the readiness decisions tied to cash.

Capacity Impact

Week 32 exposure remains 125,000 pcs if K-4 cannot start.

Suggested Action

Arrange Rs 2.40 Cr working capital by 10-Aug.

Traceability

DashboardOrdersFull KitCapacityCashRecommendations
21-Aug-2026

Lowest cash point

Action Required

Runway Low

-Rs 1.10 Cr

The plan reaches the worst forecast point before receipts recover.

K-4, K-11
28-Aug-2026

Buyer receipts begin

Watch

Buyer Receipt

Rs 0.60 Cr

Cash turns positive again, but only after the W32 decision window.

K-1, K-3, K-11
04-Sep-2026

Recovery after receipts

Healthy

Factor Receipt

Rs 2.10 Cr

Cash recovers after receipts, but the production decision had to happen earlier.

K-5, K-7