K-4
Fabric release required
- Cash Impact
- Fabric release increases the near-term cash requirement.
- Working Capital Impact
- Part of Rs 2.40 Cr cover
- Suggested Action
- Expedite fabric and secure cash cover by 10-Aug.
G3CT
Garment Capacity & Cash Control Tower
Cash
Cash constraint decisions for Base Plan - Week 32.
Base Plan
Scenario
Week 32
Planning
Mock
Data
Executive Summary
Cash becomes a production constraint when K-4 fabric release needs cover before receipts recover. The first negative date is 14-Aug and the prevention action is Rs 2.4 Cr cover before 10-Aug.
First decision
Secure Rs 2.40 Cr cash cover before 10-Aug.
Current Cash
Rs 3.80 Cr
Lowest Cash Position
-Rs 1.10 Cr
Negative Cash Date
14-Aug
Working Capital Required
Rs 2.40 Cr
Cash Flow Timeline
The timeline explains why the balance moves: fabric release, vendor hold, delayed receipts, and the bridge cover decision.
Positive cash zone
Opening cash is positive before material commitments land.
Negative cash zone
14-Aug is the first negative date and 21-Aug is the low point.
Recovery point
Receipts recover after the W32 production decision is due.
Cash Health
Current Position
Rs 3.80 Cr
Opening cash is positive
Near-Term Risk
Negative on 14-Aug
Supplier payments exceed receipts
Working Capital
Rs 2.40 Cr
Cover required before 10-Aug
Recovery Outlook
Positive by 28-Aug
Buyer receipts begin
Cash Constraint Drivers
| Driver | Impact | Orders Affected | Recommended Action |
|---|---|---|---|
Fabric Release | Part of Rs 2.40 Cr cover; K-4 fabric is blocked until cash is secured | K-4, K-13 | Secure cash cover and release K-4 fabric |
Vendor Hold | Ready work cannot convert into runnable work if payment or credit is not cleared | K-11 | Negotiate vendor credit or approve release payment |
Timing Gap | Material payments arrive before buyer receipts and push cash below zero | K-4, K-7, K-11 | Align receipts and arrange bridge funding |
Cash Event Log
| Date | Event | Amount | Related Orders | Event Type |
|---|---|---|---|---|
| 31-Jul-2026 | Opening cash position | Rs 3.80 Cr | K-1, K-2 | Opening Balance |
| 07-Aug-2026 | Material advances for K-4, K-7, K-11 | Rs 1.20 Cr | K-4, K-7, K-11 | Fabric Payment |
| 14-Aug-2026 | Supplier payments exceed receipts | -Rs 0.40 Cr | K-4, K-13, K-11 | Cash Constraint |
| 21-Aug-2026 | Lowest cash point | -Rs 1.10 Cr | K-4, K-11 | Runway Low |
| 28-Aug-2026 | Buyer receipts begin | Rs 0.60 Cr | K-1, K-3, K-11 | Buyer Receipt |
| 04-Sep-2026 | Recovery after receipts | Rs 2.10 Cr | K-5, K-7 | Factor Receipt |
Daily Cash Flow Table
| Date | Opening Cash | Inflow | Outflow | Closing Cash | Main Driver |
|---|---|---|---|---|---|
| 31-Jul | Rs 3.80 Cr | Rs 0.00 Cr | Rs 0.00 Cr | Rs 3.80 Cr | Opening cash position |
| 03-Aug | Rs 3.80 Cr | Rs 0.20 Cr | Rs 1.40 Cr | Rs 2.60 Cr | K-4 fabric release preparation |
| 07-Aug | Rs 2.20 Cr | Rs 0.30 Cr | Rs 1.30 Cr | Rs 1.20 Cr | K-4, K-7, K-11 material advances |
| 10-Aug | Rs 1.20 Cr | Rs 0.40 Cr | Rs 1.20 Cr | Rs 0.40 Cr | K-4 fabric release deadline |
| 14-Aug | Rs 0.40 Cr | Rs 0.20 Cr | Rs 1.00 Cr | -Rs 0.40 Cr | Supplier payments exceed receipts |
| 21-Aug | -Rs 0.40 Cr | Rs 0.40 Cr | Rs 1.10 Cr | -Rs 1.10 Cr | Lowest cash point |
| 28-Aug | -Rs 1.10 Cr | Rs 2.00 Cr | Rs 0.30 Cr | Rs 0.60 Cr | Buyer receipts begin |
| 04-Sep | Rs 0.60 Cr | Rs 1.90 Cr | Rs 0.40 Cr | Rs 2.10 Cr | Factor receipts complete recovery |
Critical Cash Risks
K-4
Fabric release required
K-11
Vendor payment hold
K-13
Trim closure timing
Constraint Analysis
K-4 cash to capacity chain
K-11 ready order hold
Timing gap to cash constraint
Receipt delay to throughput risk
Cash Detail Table
The first negative event opens by default so the K-4, Full Kit, capacity, and recommendation links are visible immediately.
| Date | Event | Amount | Impact | Related Orders | |
|---|---|---|---|---|---|
| 31-Jul-2026 | Opening cash position Healthy Opening Balance | Rs 3.80 Cr | The base plan starts positive, but material advances are approaching. | K-1, K-2 | |
| 07-Aug-2026 | Material advances for K-4, K-7, K-11 Watch Fabric Payment | Rs 1.20 Cr | Cash runway narrows before K-4 fabric release and K-11 vendor hold are cleared. | K-4, K-7, K-11 | |
| 14-Aug-2026 | Supplier payments exceed receipts Action Required Cash Constraint | -Rs 0.40 Cr | Cash becomes a constraint and can stop the production recovery plan. | K-4, K-13, K-11 | |
Why It Matters Orders Affected K-4 (At Risk - Full Kit), K-13 (At Risk - Trim Gap), K-11 (At Risk - Cash Hold) Full Kit Impact K-4 fabric and K-13 trims remain the readiness decisions tied to cash. Capacity Impact Week 32 exposure remains 125,000 pcs if K-4 cannot start. Suggested Action Arrange Rs 2.40 Cr working capital by 10-Aug. Traceability DashboardOrdersFull KitCapacityCashRecommendations | |||||
| 21-Aug-2026 | Lowest cash point Action Required Runway Low | -Rs 1.10 Cr | The plan reaches the worst forecast point before receipts recover. | K-4, K-11 | |
| 28-Aug-2026 | Buyer receipts begin Watch Buyer Receipt | Rs 0.60 Cr | Cash turns positive again, but only after the W32 decision window. | K-1, K-3, K-11 | |
| 04-Sep-2026 | Recovery after receipts Healthy Factor Receipt | Rs 2.10 Cr | Cash recovers after receipts, but the production decision had to happen earlier. | K-5, K-7 | |